Session of 2025
SENATE BILL No. 233
By Committee on Federal and State Affairs
2-6
1AN ACT concerning energy; relating to commercial wind and solar energy
2facilities; establishing requirements for the decommissioning of such
3facilities; requiring a county to enter into a decommissioning agreement
4with a facility owner prior to construction of any such facility;
5requiring the facility owner to provide financial assurance in an amount
6sufficient to cover the costs of decommissioning; requiring
7decommissioning costs to be paid by affected landowners under certain
8circumstances.
9
10Be it enacted by the Legislature of the State of Kansas:
11Section 1. (a) (1) Prior to the construction of any commercial solar
12energy facility or commercial wind energy facility in this state, the board
13of county commissioners of the county where such proposed facility will
14be located shall require the facility owner to enter into a decommissioning
15agreement with the county. The decommissioning agreement shall
16establish a sufficient, efficient and enforceable decommissioning plan for
17the facility. The decommissioning plan shall require a facility owner to
18decommission all generating units and applicable supporting facilities and
19materially return and restore any land disturbed or changed as a result of
20the construction, operation and decommissioning of the facility to the
21condition that such land existed prior to such construction, operation and
22decommissioning.
23(2) The decommissioning plan shall be prepared by an independent,
24third-party engineer licensed under the laws of this state. Such plan shall
25include an estimate and description of the amount of financial assurance
26that shall be sufficient for the facility owner to implement the
27decommissioning plan. Such financial assurance cost estimate shall be
28updated by such an engineer at least once every five years to account for
29any inflation adjustments or other factors. The facility owner shall
30reimburse the county for any costs borne by the county to contract with an
31engineer pursuant to this section.
32(3) The facility owner shall provide the financial assurance
33determined pursuant to paragraph (2) in the form of an irrevocable standby
34letter of credit, performance bond, surety bond or unconditional payment
35guarantee executed by a parent company of the facility owner only if such
36parent company maintains an investment grade credit rating. The county
1shall have the sole authority to determine the form of financial assurance
2required pursuant to a decommissioning plan and may, from time to time
3and as conditions may require, revise the form of financial assurance
4required. Such financial assurance shall at all times be accessible by such
5county so that the county may initiate decommissioning of the facility in
6accordance with the terms and conditions of the decommissioning
7agreement.
8(b) Upon any change of ownership of a commercial solar energy
9facility or commercial wind energy facility, a decommissioning agreement
10entered into pursuant to this section shall be transferred to and all such
11rights and obligations assumed by the subsequent facility owner.
12(c) If a facility owner indicates an inability to complete
13decommissioning, or is no longer in business, and the county is unable to
14access the financial assurance to complete decommissioning in accordance
15with a decommissioning plan entered into pursuant to this section, the
16county shall decommission such facility in accordance with the
17decommissioning plan and shall assess against any landowner who is
18subject to a lease or easement relating to such facility the costs borne by
19the county to decommission any such facility on such landowner's land.
20Prior to the county bearing the costs to decommissioning any such facility
21and assessing such costs against landowners as provided in this subsection,
22the county may authorize any landowner to decommission any such
23facility and may establish reasonable time limitations for the landowner's
24completion of such decommissioning.
25(d) Any decommissioning agreement entered into pursuant to this
26section shall include meaningful remedy and penalty provisions for a
27facility owner's noncompliance with such agreement, including a
28requirement that when the county commences a civil action against a
29facility owner with respect to the enforcement or interpretation of a
30decommissioning agreement, the county shall be entitled to an award of
31the county's costs of such litigation, including reasonable attorney fees,
32from the facility owner. The county shall have authority to enforce a
33decommissioning agreement by mandamus or other appropriate
34proceeding at law or equity.
35(e) As used in this section:
36(1) "Commercial solar energy facility" means any device or assembly
37of devices and supporting facilities that has a nameplate capacity of a least
38one megawatt and uses solar energy to generate electricity for the primary
39purpose of wholesale or retail sale.
40(2) "Commercial wind energy facility" means any device or assembly
41of devices and supporting facilities that has a nameplate capacity of at
42least one megawatt and uses kinetic energy from the wind to generate
43electricity for the primary purpose of wholesale or retail sale.
1(3) "Facility owner" means any person who has a direct ownership
2interest in or who is acting as the developer or operator of a commercial
3solar energy facility or commercial wind energy facility.
4Sec. 2. This act shall take effect and be in force from and after its
5publication in the statute book.