Prev | Article 1. - POWER PLANT DAMS | Next |
82a-114. No action for damages occasioned by the erection of a milldam shall be hereafter sustained unless such action be brought within two years after the erection of said dam, nor any action for the maintenance of a dam already erected unless brought within one year after the passage of this act. |
History: L. 1867, ch. 87, § 14; G.S. 1868, ch. 66, § 14; R.S. 1923, 59-114. |